Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

FDOT: Treasure Coast Traffic Report Through Friday November 10

 Treasure Coast Traffic Report Through Friday November 10
Jevanto Productions - stock.adob
/
298379174
Treasure Coast Traffic Report Through Friday November 10

Treasure Coast - Monday November 6, 2023:   Treasure Coast traffic will be affected this week by ongoing construction projects and maintenance work in Martin, St. Lucie and Indian River counties.

CONSTRUCTION PROJECTS

MARTIN COUNTY

(Hobe Sound, Palm City, City of Stuart, Stuart, Jensen Beach, Jupiter Island, Port Salerno, Rio, Indiantown, Tequesta, Town of Sewall’s Point)

1. State Road 714/SW Martin Highway Widening Project
Description: This 1.127-mile widening project began on August 6, 2021. Project improvements include widening SR 714/SW Martin Highway from a two-lane undivided rural roadway to a four-lane divided urban roadway, widening the bridge over Florida’s Turnpike, constructing seven-foot buffered bike lanes and six-foot sidewalks on both sides of the roadway, and installing signing, signalization, and lighting upgrades.
Cost/Completion: $21.3 million. Completion is expected in fall 2024.
Traffic Impact:

  • The eastbound and westbound shoulders on SR 714/SW Martin Highway from SW Martin Downs Boulevard to SW Citrus Boulevard are closed through mid-2024 to facilitate widening activities. Cyclists and motorists should share the road.
  • One lane in either direction of SR 714/SW Martin Highway from Citrus Boulevard to Martin Downs Boulevard may be closed, Monday through Thursday, between 8 p.m. to 6 a.m., for roadway construction. During this time, intermittent side street closures may occur, and two-way traffic will be maintained by a flagging operation.
  • SW Leighton Farms Avenue between SR 714/SW Martin Highway and SW Honey Terrace may be closed to traffic overnight, from 8 p.m. until 5 a.m., Wednesday, Nov. 1 through Thursday, Nov. 30, for roadway construction. Monday, Dec. 4 through Friday, Dec. 8, will be used as contingency nights if needed.

Detour Information:

    • Eastbound and westbound SR 714/SW Martin Highway to southbound SW Leighton Farm Avenue motorists will be detoured via SR 714/SW Martin Highway, SW Citrus Boulevard, and SW Moore Street to SW Leighton Farm Avenue.
    • Northbound and southbound SW Leighton Farm Avenue to SR 714/SW Martin Highway motorists will be detoured via SW Moore Street and SW Citrus Boulevard will be detoured via SW Moore Street and SW Citrus Boulevard to SR 714/SW Martin Highway.
    • Northbound and southbound SW Citrus Boulevard to SW Leighton Farm Avenue motorists will be detoured via SW Citrus Boulevard and SW Moore Street to SW Leighton Farm Avenue.
    • Local traffic between SR 714/SW Martin Highway and SW Moore Street will be escorted through the work zone by project personnel and off-duty police officers.
  • Eastbound and westbound SR 714/SW Martin Highway between SW Citrus Boulevard and SW Leighton Farm Avenue may be closed to traffic overnight, from 8 p.m. until 5 a.m., Wednesday, Nov. 1 through Thursday, Nov. 30, for roadway construction. Monday, Dec. 4 through Friday, Dec. 8, will be used as contingency nights if needed.

Small Vehicle Detour Information:

    • Small vehicle westbound SR 714/SW Martin Highway traffic will be detoured via SW Leighton Farm Avenue, SW Moore Street, and SW Citrus Boulevard to SR 714/SW Martin Highway.
    • Small vehicle eastbound SR 714/SW Martin Highway traffic will be detoured via SW Citrus Boulevard, SW Moore Street, and SW Leighton Farm Avenue to SR-714/SW Martin Highway.
    • Southbound SW Citrus Boulevard to eastbound SR 714/SW Martin Highway small vehicle traffic will be detoured via SW Citrus Boulevard, SW Moore Street, and SW Leighton Farm Avenue to SR-714/SW Martin Highway.
    • Local traffic between SW Citrus Boulevard and SW Leighton Farm Avenue will be escorted through the work zone by project personnel and off-duty police officers.

Three or More Axle Truck and Trailer Detour Information:

    • Three or more axle trucks and trailer eastbound SR 714/SW Martin Highway traffic will be detoured via SW Citrus Boulevard, SW 96th Street, SR 76/SW Kanner Highway, enter the SR 9/I-95 northbound on-ramp from SW Kanner Highway, exit SR 9/I-95 at High Meadows Avenue (Exit 102), High Meadows Avenue to SR 714/SW Martin Highway.
    • Three or more axle trucks and trailer westbound SR 714/SW Martin Highway traffic will be detoured via High Meadows Avenue, enter the SR 9/I-95 southbound on-ramp from High Meadows Avenue, exit SR 9/I-95 at SR 76/SW Kanner Highway (Exit 101), SW 96th Street, and SW Citrus Boulevard to SR 714/SW Martin Highway.
    • Local traffic on SR 714/SW Martin Highway between SW Leighton Farm Avenue and SW Citrus Boulevard will be escorted through the work zone by project personnel and off-duty police officers.
  • SW Citrus Boulevard at SR 714/SW Martin Highway, may be closed to traffic overnight, from 8 p.m. until 5 a.m., Wednesday, Nov. 1 through Thursday, Nov. 30 for roadway construction. Monday, Dec. 4 through Friday, Dec. 8 will be used as contingency nights if needed.

Detour Information:

    • Eastbound SR 714/SW Martin Highway to southbound SW Citrus Boulevard motorists will be detoured via SW Leighton Farm Avenue and SW Moore Street to SW Citrus Boulevard.
    • Southbound SW Citrus Boulevard motorists continuing south on the roadway will be detoured via SR 714/SW Martin Highway, SW Leighton Farm Avenue, and SW Moore Street to SW Citrus Boulevard.
    • Northbound SW Citrus Boulevard motorists continuing north on the roadway will be detoured via SW Moore Street, SW Leighton Farm Avenue and SR 714/SW Martin Highway to SW Citrus Boulevard.
    • Local traffic between SR 714/SW Martin Highway and SW Moore Street will be escorted through the work zone by project personnel and off-duty police officers.
  • The eastbound traffic on SR 714/SW Martin Highway just west of SW Citrus Boulevard was shifted to the newly constructed roadway to allow for westbound road construction through February 2024. Eastbound traffic attempting to access driveways on the north side of SR 714/SW Martin Highway will be required to make U-turns on SW 42nd Avenue, Martin Downs Highway, and SW Citrus Boulevard. Eastbound traffic attempting to leave the driveways on the northside will be required to make U-turns at SW 42nd Avenue and SW Citrus Boulevard. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

2.State Road 76/Kanner Highway Resurfacing Project
Description: This 1.4-mile resurfacing project from north of Cabana Point Circle to SR 5/US 1 in the City of Stuart began on Monday, July 25, 2022. Project improvements include milling and resurfacing the existing roadway; some minor widening will occur along northbound and southbound SR 76/Kanner Highway; upgrading crosswalks and curb ramps to meet Americans with Disabilities Act (ADA) standards; installing sidewalks, signage and pavement markings; upgrading pedestrian lighting at two signalized intersections at SR 714/Monterey Road and SR 5/US 1; and, upgrading or restoring drainage pipes and replacing sections of the City of Stuart’s watermain at various locations.
Cost/Completion: $5,064,094.62. Completion is expected summer 2023.
Traffic Impact:

  • One southbound and northbound lane of SR 76/Kanner Highway from the Monterey Road intersection to SR 5/US 1 may be closed from 8 a.m. to 4 p.m. as needed from Monday, Sept. 25, through Friday, Nov. 17, for sign installation punch work and site restoration.
  • Up to two southbound and northbound lanes of SR 76/Kanner Highway from SW Cabana Point to SR 5/US 1 may be closed from 8 p.m. to 6:30 a.m. as needed from Monday, October 9, through Sunday, Nov. 19, for thermoplastic pavement marking installation. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 

3. State Road (SR) 5/US 1 Resurfacing Project, from SE Contractors Way to north of SR 732/Jensen Beach Boulevard
Description: This 5.042-mile resurfacing project began on June 19, 2023. The project improvements on SR 5/US 1 consist of milling and resurfacing the existing roadway excluding SW Joan Jefferson Way to NW Wright Boulevard (no work on the Roosevelt Bridge), drainage improvements, constructing sidewalks to fill in missing gaps, upgrading curb ramps to meet Americans with Disabilities Act (ADA) standards, installing pedestrian pushbutton detectors at signalized intersections, and upgrading pavement markings and lighting signalized intersections.
Cost/Completion: $12 million. Completion is expected in spring 2024.
Traffic Impacts:

  • One northbound lane of SR 5/US 1 from NW Wright Boulevard to NW Baker Road will be closed around-the-clock beginning at 7 a.m., Monday, Nov. 6 through approximately 7 a.m., Thursday, Nov. 9, for curb, sidewalk, and guardrail work.
  • One northbound lane of SR 5/US 1 from SR 732/NW Jensen Beach Boulevard to the north side of the Roosevelt Bridge, will be closed from 8:30 a.m. to 3:30 p.m., Monday, Nov. 6 through Thursday, Nov. 9, for silt fence installation, concrete removal, concrete pour, and directional bores.
  • One northbound lane of SR 5/US 1 from the south side of the Roosevelt Bridge to SE Contractors Way, will be closed from 8:30 a.m. to 3:30 p.m., Monday, Nov. 6 through Thursday, Nov. 9, for silt fence installation, concrete removal, concrete pour, and directional bores.
  • One southbound lane of SR 5/US 1 from SR 732/ NW Jensen Beach Boulevard to the north side of the Roosevelt Bridge will be closed from 9:30 a.m. to 4:30 p.m., Monday Nov. 6 through Thursday, Nov. 9, for silt fence installation, concrete removal, and directional bores.
  • One southbound lane of SR 5/US 1 from the south side of the Roosevelt Bridge to SE Contractors Way, will be closed from 9:30 a.m. to 4:30 p.m., Monday, Nov. 6 through Thursday, Nov. 9, for silt fence installation, concrete removal, concrete pour, and directional bores. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 

4. State Road (SR) 76/Kanner Highway Resurfacing and Improvements Project, from north of SR 710/Warfield Boulevard to St. Lucie Mobile Village
Description: The project began on July 26, 2023. The project improvements consist of repaving and restriping the existing roadway and shoulders, widening the existing shoulders from 10 feet to 12 feet, upgrading signing and pavement markings, installing audible vibratory treatment along the centerline and edge lines of the roadway, extending the existing guardrail at selected locations to address canal hazards, regrading the existing ditch in front of St. Lucie Mobile Village, and replacing the existing Traffic Monitoring Site (TMS) loops.
Cost/Completion: $2,771,566.18. Completion is expected in spring 2024.
Traffic Impacts:

  • One lane of SR 76/Kanner Highway from approximately 2,000 feet north of SW Jupiter Indiantown Road to approximately 1,000 feet north of St. Lucie Mobile Village will undergo a moving lane closure from 7 a.m. to 5 p.m., Monday, Nov. 6 through Thursday, Nov. 9 for shoulder widening and guardrail work. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

5. SR 15/US 98 Resurfacing Project
Description: This 12.333-mile project began on August 4, 2023. The project improvements consist of milling and resurfacing the existing roadway, widening the roadway shoulders to 12 feet (7 feet paved and 5 feet unpaved), and installing new pavement markings.
Cost/Completion: $20.8 Million. Completion is expected in late 2024.
Traffic Impacts:

  • One lane in either direction of SR 15/US 98 from the Palm Beach/Martin County line to the Martin/Okeechobee County line will be closed from 7 a.m. to 7 p.m., Monday, Nov. 6 through Friday, Nov. 9 for survey, paving, embankment and clearing work. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

6. Dynamic Envelope Marking Rail Safety Project
Description: Construction on this railroad marking project will take place at SW Tommy Clements Street, SW Silver Fox Lane, and SW Dr. Martin Luther King Jr. Drive in Indiantown, Innovation Drive in Jupiter, Aviation Road in West Palm Beach, Larrimore Road in Pahokee, Gator Boulevard/Airport Road, NW 12th Street/Osceola Street, W Canal Street, NW Avenue D, SW Avenue E/Dr. M.L.K. Jr. Boulevard W in Belle Glade, NW 1st Avenue in South Bay, and Miami Canal Road in Lake Harbor began on August 28, 2023. Work includes milling and resurfacing the pavement, installing signage, pavement markings, and sod, and performing utility adjustments.
Cost/Completion: $1.1 million/Early 2024
Traffic Impacts:

  • No lane closures. For more information, contact Community Outreach Specialist Melissa Readling at 772-577-8803 or mreadling@corradino.com.

7. State Road (SR) 732/Jensen Beach Causeway Mobility Improvements Project
Description: The SR 732/Jensen Beach Causeway construction work began September 19, 2023. The length of the project is 1.842 miles from NE Indian River Drive to SR A1A. Project improvements consist of milling and resurfacing the existing roadway, replacing damaged sidewalk, upgrading pedestrian curb ramps to meet Americans with Disabilities Act (ADA) standards, upgrading signing and markings to provide buffered bicycle lanes, and replacing the existing bridge lighting, pendant lighting, and decorative pier lights.
Cost/Completion: $3 Million. Completion is expected Summer 2024.
Traffic Impact:

  • No lane closures. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 

ST. LUCIE COUNTY

(City of Port St. Lucie, Port St. Lucie, White City, City of Fort Pierce, Fort Pierce, Okeechobee, St. Lucie West, Tradition)

8. SW Port St. Lucie Boulevard Widening Project, from South of SW Alcantarra Boulevard to South of SW Darwin Boulevard
Description: Construction on this 0.713-mile widening project began on Thursday, January 27, 2022, in the City of Port St. Lucie. The City of Port St. Lucie, as Project Sponsor, requested the Florida Department of Transportation (FDOT), District Four design and construct this project through application to the St. Lucie Transportation Planning Organization and City of Port St. Lucie Resolution 18-R42. Project improvements include widening SW Port St. Lucie Boulevard from a two-lane undivided roadway to a four-lane divided roadway, installing three new signalized intersections with mast arms at SW Alcantarra Boulevard, SW Tulip Boulevard, and SW Tunis Boulevard, adding a right turn lane on SW Port St. Lucie Boulevard’s north approach to SW Alcantarra Boulevard, constructing an 18’ wide raised median with curb and gutter, upgrading crosswalks and curb ramps to meet Americans with Disabilities Act (ADA) standards, constructing 8’-10’ wide sidewalks on both sides of SW Port St. Lucie Boulevard for pedestrian and bicycle use, and 6’ wide sidewalks on side streets, installing a new closed drainage system, signing, pavement markings, signalization, and lighting upgrades, and landscaping for the median including trees, irrigation and stamped concrete.
Cost/Completion: $11,570,179. Completion is expected summer 2024.
Traffic Impact:

  • One lane in either direction of SW Port St. Lucie Boulevard between SW Fisherman Avenue and SW Darwin Boulevard may be closed Monday through Friday through November 2023, from 9 a.m. to 3 p.m. to install drainage structures. Flagging operations will be in place to direct traffic.
  • Beginning at 8 a.m. Monday, November 6, 2023, SW Trouville Avenue at SW Port St. Lucie Boulevard, will be closed through approximately 3 p.m., Friday, November 17, 2023, for drainage work across the roadway.

Detour Information:

      • Northbound and southbound SW Port St. Lucie Boulevard to eastbound SW Trouville Avenue will be detoured to eastbound SW Tulip Boulevard to southbound SW Voyager Street to westbound SW Trouville Avenue.
      • Westbound SW Trouville Avenue motorists will be detoured to northbound SW Voyager Street to westbound SW Tulip Boulevard to SW Port St. Lucie Boulevard. Please see flyer attached.
  • Beginning at 8 a.m. Monday, November 6, 2023, SW Tunis Avenue at SW Port St. Lucie Boulevard, will be closed through approximately 3 p.m., Friday, November 17, 2023, for drainage work across the roadway.

Detour Information:

      • Northbound and southbound SW Port St. Lucie Boulevard to eastbound SW Tunis Avenue will be detoured to eastbound SW Rice Avenue/SW Chartwell Street to westbound SW Tunis Avenue.
      • Westbound SW Tunis Avenue motorists will be detoured to southbound SW Chartwell Street/SW Rice Avenue to SW Port St. Lucie Boulevard. 
      • Please note, the entrance on SW Tunis Avenue to Darwin Square will remain open. Lucie Boulevard.
  • Beginning at 8 a.m. Monday, November 6, 2023, SW Rice Avenue at SW Port St. Lucie Boulevard, will be closed through approximately 3 p.m., Friday, November 17, 2023, for drainage work across the roadway.

Detour Information:

      • Northbound and southbound SW Port St. Lucie Boulevard to eastbound SW Rice Avenue will be detoured via SW Tunis Avenue and SW Chartwell Street to SW Rice Avenue.
      • Westbound SW Rice Avenue motorists will be detoured via SW Chartwell Street and SW Tunis Avenue to SW Port St. Lucie Boulevard.
  • Beginning at 8 a.m. Monday, November 6, 2023, SW Thrift Avenue at SW Port St. Lucie Boulevard, will be closed through approximately 3 p.m., Friday, November 17, 2023, for drainage work across the roadway.

Detour Information:

      • Northbound and southbound SW Port St. Lucie Boulevard to eastbound SW Thrift Avenue motorists will be detoured via SW Trouville Avenue and SW Voyager Street to SW Thrift Avenue.
      • Westbound SW Thrift Avenue motorists will be detoured via SW Voyager Street and SW Trouville Avenue to SW Port St. Lucie Boulevard.
  • Advanced Notice: Beginning at 8 a.m. Monday, November 13, 2023, S Globe Avenue at SW Port St. Lucie Boulevard, will be closed around-the-clock through approximately 3 p.m. Friday, November 17, 2023, for drainage work across the roadway. Monday, Nov. 27 through Friday, Dec. 1 will be used as contingency dates if needed.

Detour Information:

    • Northbound and southbound SW Port St. Lucie Boulevard to westbound S Globe Avenue will be detoured via SW North Globe Avenue and W Globe Avenue to S Globe Avenue.
    • Eastbound S Globe Avenue motorists will be detoured via W Globe Avenue and SW North Globe Avenue to SW Port St. Lucie Boulevard. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

City of Port St. Lucie project/adjacent to project corridor:
The Port St. Lucie Boulevard South Project Segment 3, managed by the City of Port St. Lucie, is reconstructing approximately 0.7 miles of the existing four-lane roadway from SW Gatlin Boulevard to SW Darwin Boulevard and a portion of SW Darwin Boulevard through Winter 2023.
Traffic Impact:

  • Speed limit lowered to 30 mph for the duration of the construction project.
  • Closure of existing median openings at both SW Yale Street and SW Cairo Avenue.
  • One northbound through lane will be eliminated on SW Port St. Lucie Boulevard north of SW Aurelia Avenue to Gatlin Boulevard, leaving one through lane and one dedicated left turn lane onto westbound Gatlin Boulevard. For more information about the City of Port St. Lucie’s Segment 3 Project, please contact Beth Zsoka, Project Public Information Specialist at 772-871-5176.

9. St. Lucie West Boulevard Widening Project, from Commerce Center Drive to Peacock Boulevard
Description: This 1.814-mile widening project began on Monday, January 24, 2022, in the City of Port St. Lucie. The City of Port St. Lucie, as Project Sponsor, requested the Florida Department of Transportation (FDOT), District Four design and construct this project through application to the St. Lucie Transportation Planning Organization and City of Port St. Lucie Resolution 20-R75. Project improvements include constructing a new 3-lane eastbound bridge over I-95, separated 10-feet from the existing bridge; widening St. Lucie West Boulevard to accommodate two (2) eastbound and westbound travel lanes, with a third eastbound lane between the I-95 southbound and northbound ramps, two (2) eastbound left turn lanes at the I-95 northbound on ramp, two (2) westbound right turn lanes at the I-95 northbound on ramp; reconstructing/widening the I-95 ramps; connecting the existing St. Lucie West Boulevard roadway to the new eastbound bridge from the east and west directions; constructing 7-foot buffered bike lanes/paved shoulder and 5-foot to 6-foot wide sidewalks on both sides of the roadway; constructing a 22-foot to 40-foot lane-line to lane-line curbed median with curb and gutter; installing fencing retrofits on the north side of the existing bridge, and new railing on the eastbound bridge; and, installing new traffic signals with enhanced synchronization and timing at I-95 ramps.
Cost/Completion: $15,518,729. Completion is expected winter 2023.
Traffic Impact:

  • The eastbound lane of St. Lucie West Boulevard from the I-95 northbound off-ramp intersection to Peacock Boulevard was shifted 3-feet to the south to facilitate roadway construction through December 2023.
  • Eastbound St. Lucie West Boulevard to southbound I-95 traffic is shifted to the newly paved permanent on-ramp.
  • Eastbound traffic on St. Lucie West Boulevard is shifted to the new roadway/bridge outside lane to facilitate roadway construction through December 2023.
  • The bike lane and shoulder along the new eastbound St. Lucie West Boulevard will be open and can be used by bicycles. The asphalt pathway along westbound St. Lucie West Boulevard will be open and can be used by bicycles through December 2023.
  • Traffic on the northbound I-95 on-ramp was shifted to permanent configuration from westbound St. Lucie West Boulevard. The free-flowing right turn lane from westbound St. Lucie West Boulevard onto the northbound I-95 on-ramp was eliminated. A new right turn lane from westbound St. Lucie West Boulevard onto the northbound I-95 entrance ramp was added, and motorists will stop at the signal before turning onto the ramp.
  • Traffic on the northbound I-95 exit ramp to St. Lucie West Boulevard is split to one inside (left) and one outside (right) lanes to facilitate roadway construction operations through December 2023.
  • Traffic on the southbound I-95 exit ramp to St. Lucie West Boulevard is split to one inside (left) and one outside (right) lanes to facilitate roadway construction activities through December 2023.
  • Intermittent shoulder closures may occur Monday through Friday, through December 2023, from 7 a.m. to 5 p.m. for road work at the following locations:
    • Northbound and southbound I-95 mainline from just north and south of the St. Lucie West Boulevard overpass.
    • All I-95 entrance and exit ramps at St. Lucie West Boulevard
    • Eastbound and westbound St. Lucie West Boulevard from Champions Way to SW Peacock Boulevard
  • One lane in either direction of St. Lucie West Boulevard between Champions Way and SW Peacock Boulevard may be intermittently closed nightly Monday through Friday, through December 2023, from 10 p.m. to 6 a.m. for roadway work. A flagging operation will be in place to help direct traffic.
  • One northbound and southbound lane of I-95 may be intermittently closed from just north and south of the St. Lucie West Boulevard overpass Monday through Friday, through December 2023, from 7 a.m. to 5 p.m., for roadway work.
  • One northbound and southbound lane of I-95 may be intermittently closed from just north and south of the St. Lucie West Boulevard overpass Monday through Friday, through December 2023, from 8 p.m. to 6 a.m., for roadway work. No more than one lane will be closed at a time in either direction of I-95. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 

10. State Road 9/I-95 Northbound and Southbound Off-Ramps at Gatlin Boulevard Roadway Improvements Project
Description: This 1.4-mile roadway improvements project began on Friday, June 10, 2022. Project improvements include widening southbound I-95 to provide a 12-foot auxiliary lane and a 12-foot shoulder (10-feet paved); widening I-95 southbound Gatlin Boulevard off-ramp for the addition of a right-turn lane and a left-turn lane; widening the inside of the I-95 northbound Gatlin Boulevard off-ramp to provide three (3) left-turn lanes; widening eastbound and westbound Gatlin Boulevard to provide three 15-foot left-turn lanes; modifying drainage to an open system with dry ponds; installing one cantilever sign structure at the southbound I-95 off-ramp; and adding new signing and pavement markings.
Cost/Completion: $4,627,785.77. Completion is anticipated fall 2023.
Traffic Impact:

  • The outside or inside ramp lane of the northbound I-95 to eastbound and westbound Gatlin Boulevard exit ramps may be closed from 9 a.m. to 4 p.m., Monday through Friday, through November 2023, for roadway work. 
  • The outside or inside ramp lane of the southbound I-95 to eastbound and westbound Gatlin Boulevard exit ramps may be closed from 9 a.m. to 4 p.m., Monday through Friday, through November 2023, for roadway work.  
  • The outside shoulder of the southbound I-95 to eastbound and westbound Gatlin Boulevard exit ramp is closed around-the-clock through November 2023 to facilitate roadway work.  
  • One westbound outside lane of Gatlin Boulevard from just west of the I-95 northbound on-ramp entrance to just east of the overpass is closed around-the-clock through November 2023, for roadway work.  
  • One lane in each direction of Gatlin Boulevard from just east and west of the northbound and southbound I-95 off-ramps at Gatlin Boulevard may be closed from 7 a.m. to 5 p.m., Monday through Friday, through November 2023, for clearing and grubbing, and sidewalk work. During this time, sections of the sidewalks will be closed, and pedestrian detours will be in place.  
  • One southbound lane of I-95 from just before and at the off-ramp to Gatlin Boulevard may be closed nightly, Sunday through Thursday, through November 2023, from 9 p.m. to 6 a.m., for sign installation. Traffic on the outside lane will be temporarily shifted to the left during the lane closure. FHP will be onsite to assist motorists.
  • Two eastbound and westbound lanes of Gatlin Boulevard between east of SW Village Parkway and just east of the SR 9/I-95 on-ramp will be closed to traffic overnight, 9 p.m. to 6 a.m., Sunday, Nov. 5 through Thursday, Nov. 9, for roadway paving operations.
  • The SR 9/I-95 northbound off-ramp to eastbound and westbound Gatlin Boulevard may be closed to traffic overnight, 9 p.m., until 6 a.m., Sunday through Thursday, beginning Sunday, Nov. 5 through Thursday, Nov. 9, for milling and resurfacing work. Sunday, Nov. 12 through Thursday, Nov. 30 will be used as contingency nights if needed. During this closure, motorists will be detoured via the SR 9/I-95 northbound off-ramp to Becker Road (Exit 114), SW Becker Road, and Port St. Lucie Boulevard to Gatlin Boulevard. FHP will be on site to assist motorists. Only one ramp will be closed at a time.
  • The SR 9/I-95 southbound off-ramp to eastbound and westbound Gatlin Boulevard may be closed to traffic overnight, 9 p.m., until 6 a.m., Sunday through Thursday, beginning Sunday, Nov. 5 through Thursday, Nov. 9, for milling and resurfacing work. Sunday, Nov. 12 through Thursday, Nov. 30 will be used as contingency nights if needed. During this closure, motorists will be detoured via the SR 9/I-95 southbound off-ramp to Crosstown Parkway (Exit 120), Crosstown Parkway, and SW Village Parkway to Gatlin Boulevard. FHP will be on site to assist motorists. Only one ramp will be closed at a time.
  • The westbound left turn lane from Gatlin Boulevard to the southbound I-95 on-ramp will be closed to traffic overnight, 9 p.m. to 6 a.m., Sunday, Nov. 5 through Thursday, Nov. 9, for paving operations. Motorists will be detoured via westbound Gatlin Boulevard, make a U-turn at the Gatlin Boulevard and SW Village Parkway intersection, to the southbound I-95 on-ramp.
    • The eastbound left turn lane from Gatlin Boulevard to northbound I-95 on-ramp will be closed to traffic overnight, 9 p.m. to 6 a.m., Sunday, Nov. 5 through Thursday, Nov. 9, for paving operations. Motorists will be detoured via eastbound Gatlin Boulevard, make a U-turn at the Gatlin Boulevard and Brescia Street intersection, to the northbound I-95 on-ramp. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 

11. State Road 9/I-95 Northbound and Southbound Off-Ramps at Midway Road Improvements Project
Description: This roadway improvements project began on November 10, 2022. The project improvements consist of adding a second left-turn lane to both the SR 9/I-95 northbound and southbound off-ramps at Midway Road (Exit 126); widening and repaving the existing SR 9/I-95 off-ramps; upgrading traffic signals with new mast arm poles and improving signalization timing and alignment; implementing Wrong Way Driving Countermeasure Systems; and upgrading existing highway lighting along with implementation of new signing and pavement markings.
Cost/Completion: $2.6 million. Completion is anticipated fall 2023.
Traffic Impact:

  • The shoulder of the northbound SR 9/I-95 off-ramp at Midway Road may be intermittently closed Monday, Nov. 6 through Thursday, Nov. 9 for maintenance work.  For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 

12. State Road 615/North 25th Street/Martin Luther King Jr. Boulevard Roadway Improvements Project
Description: This project began on April 17, 2023. Project improvements consist of milling and resurfacing the existing roadway; installing 6-foot buffered bicycle lanes; upgrading pedestrian lighting at the intersection of Juanita Avenue and St. Lucie Boulevard; upgrading pedestrian curb ramps to meet Americans with Disabilities Act (ADA) standards; upgrading guardrail connections to the existing bridge railings; and upgrading signing and pavement markings.
Cost/Completion: $2.5 million. Completion is anticipated late 2023.
Traffic Impacts:

  • Up to one northbound lane from Juanita Avenue to St. Lucie Boulevard may be closed from 9 a.m. to 4 p.m., Monday through Friday, through Friday, Nov. 17 for punch work, sign installation, and shoulder corrections.
  • Up to one southbound lane from Juanita Avenue to St. Lucie Boulevard may be closed from 9 a.m. to 4 p.m., Monday through Friday, through Friday, Nov. 17 for punch work, sign installation, and shoulder corrections.
  • Up to one northbound lane of SR 615/North 25th Street/Martin Luther King Jr. Boulevard from north of Ave Q to St. Lucie Boulevard may be closed from 7 p.m. to 6 a.m. Sunday, Oct. 8 through Sunday, Nov. 19, for asphalt corrections and permanent paving markings/ thermoplastic (as needed).
  • Up to one southbound lane of SR 615/North 25th Street/Martin Luther King Jr. Boulevard from north of Ave Q to St. Lucie Boulevard may be closed from 7 p.m. to 6 a.m., Sunday, Oct. 8 through Sunday, Nov. 19, for asphalt corrections and permanent paving markings/ thermoplastic (as needed). For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

13. State Road A1A North Causeway Over the Intracoastal Waterway (ICWW) Bridge Replacement Project
Description: This project began May 1, 2023. The SR A1A North Causeway Over the Intracoastal Waterway (ICWW) Bridge Replacement project improvements consist of constructing a new high-level fixed bridge connected directly to SR 5/US 1 going over the Florida East Coast (FEC) Railroad, Old Dixie Highway, and the Intracoastal Waterway (ICWW) featuring: one 12-foot travel lane in each direction, navigational clearances of 85 feet vertical and 125 feet horizontal at the waterway channel; installing a barrier-protected 8-foot sidewalk on the south side of the bridge and a barrier-protected 12-foot shared use path on the north side of the bridge; installing 7-foot buffered bicycle lanes within the shoulders on both sides of SR A1A; constructing a 12-foot shared-use path along Old Dixie Highway to provide connectivity to the East Coast Greenway; building an observation deck beneath the west side of the new bridge structure; constructing a new access road under the bridge to businesses east of the FEC Railroad; extending Juanita Avenue from SR 5/US 1 to Old Dixie Highway; and connecting SR 5/US 1 and Old Dixie Highway along Sunny Lane.
Cost/Completion: $111.5 million. Completion is anticipated late 2027.
Traffic Impact:

  • One lane of either direction of SR A1A over the North Causeway bridge will be closed from 9 a.m. to 5 p.m., Monday, Oct. 30 through Thursday, Nov. 9, for routine maintenance. Only one direction will be closed at a time. A flagging operation will be in place to direct motorists.
  • One right turn lane on northbound US 1, from 500 feet south of the US 1/A1A intersection to the US 1/SR A1A intersection will be closed Monday Nov. 6 through Friday, Dec. 29, from 9 a.m. to 5 p.m. to install drainage structures.
  • One right turn lane on southbound SR 5/ US 1, from 500 feet north of the US 1/SR A1A intersection to the US 1/SR A1A intersection will be closed Monday Nov. 6 through Friday Dec. 29 from 9 a.m. to 5 p.m. to install drainage structure.
  • One left turn lane on southbound US 1, from 300 feet north of US 1/SR A1A intersection to the US 1/SR A1A intersection will be closed from Monday Nov. 6 through Friday Dec. 29 from 9 a.m. to 5 p.m. to install drainage structure.
  • One left turn lane on northbound US 1 from 300 feet south of the US 1/SR A1A intersection to the US 1 /SR A1A intersection will be closed from Monday Nov. 6 to Friday Dec. 29 from 9 a.m. to 5 p.m. to install drainage structure.
  • The right shoulder on northbound US 1 from 500 feet south of Juanita Avenue to 500 feet north of Juanita Avenue will be closed from 9 a.m. to 5 p.m., Monday, Nov. 6 through Friday, Dec. 29, for roadway construction.
  • Beginning at 12 a.m., Monday, Sept. 25, northbound SR 605/Old Dixie Highway at SR A1A will be closed around-the-clock through approximately 5 a.m., Friday, Dec. 22 for roadway work and drainage work. Southbound SR 605/OId Dixie Highway will remain open. Eastbound and westbound SR A1A motorists heading north on SR 605/Old Dixie Highway will be detoured via SR 5/US 1 to Naco Road.
  • The northbound lane of SR A1A between Old Dixie Highway and Shimenoke Road may be closed from 9 a.m. through 5 p.m. from Monday Sept. 25, through Friday, Dec. 22, for roadway work and drainage.
  • Beginning at 9 a.m. Monday, Nov. 20, Sunny Lane between N 3rd Street and Old Dixie Highway will be closed around-the-clock through approximately 5 p.m. Friday, Dec. 29, for drainage installation and roadway work. Local traffic will be provided access during this time. Northbound and southbound Old Dixie Highway motorists to Sunny Lane will be detoured via SR A1A and US 1 to Sunny Lane. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

14. State Road 9/I-95 Resurfacing and Safety Improvements Project, from South of Gatlin Boulevard to South of St. Lucie West Boulevard
Description: The resurfacing and safety improvements project is anticipated to begin on June 16, 2023. The project improvements consist of extending the SR-9/I-95 northbound on-ramp auxiliary lane from Gatlin Boulevard and the SR-9/I-95 southbound on-ramp auxiliary lane from St. Lucie West Boulevard, installing a Dynamic Message Sign along SR-9/I-95 northbound south of the Gatlin Boulevard interchange to provide real time messages to motorists, installing LED roadway lighting on SR-9/I-95 between Gatlin Boulevard and Crosstown Parkway, upgrading interchange signage, resurfacing SR-9/I-95 and correcting cross-slopes, and installing a Dynamic Curve Warning System north of the Gatlin Boulevard interchange to provide a warning to motorists of excessive speed and wet pavement conditions.
Cost/Completion: $9.9 million. Completion is anticipated summer 2024.
Traffic Impacts:

  • One lane in either direction of I-95 from south of Gatlin Boulevard to St. Lucie West Boulevard may be closed from 7 p.m. to 6 a.m., Sunday, Aug. 6 through Sunday, January 7, 2024, for roadway construction and bridge work.  
  • Two lanes in either direction of I-95 from south of Gatlin Boulevard to St. Lucie West Boulevard may be closed from 8 p.m. to 5 a.m., Sunday, Aug. 27 through Sunday, January 7, 2024, for roadway construction and bridge work.   
  • The northbound and southbound I-95 shoulder (right or left) from south of Gatlin Boulevard to St. Lucie West Boulevard may be closed from 8 a.m. to 4 p.m., Monday, Aug. 28, through Sunday, January 7, 2024, for foundation installation, pole construction, sign installation, lighting, and ITS work. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

15. Savannas Preserve State Park SUN Trail Improvements Project, from Walton Road to Kitterman Road
Description: The SUN Trail improvements project began July 26, 2023. Project improvements consist of constructing approximately 6.8 miles of accessible multi-use trail featuring a 10-foot-wide multi-use trail with boardwalk sections.
Cost/Completion: $10.6 million. Completion is anticipated summer 2025.
Traffic Impacts:

· All lanes are open. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

15. State Road (SR) 5/US 1 Resurfacing Project from north of SR 70/Virgina Avenue to Sunny Lane
Description: This 3-mile project is anticipated to begin Monday, November 20, 2023. The project improvements consist of milling and resurfacing the existing travel lanes with the exception of the Taylor Creek Bridge, upgrading deficient sidewalks and curb ramps, installing new pavement markings, upgrading signage, and upgrading pedestrian signals and pushbutton detectors at signalized intersections.
Cost/Completion: $6.1 Million. Completion anticipated fall 2024.

Virtual Public Meeting and In-Person Construction Open House: A Virtual Public Meeting and In-Person Construction Open House will be held on Wednesday, November 8, 2023. Please see below and the flyer attached for more information.
· The Virtual Public Meeting will be held from 5:00 p.m. to 6:00 p.m. Please use the following link to register: https://bit.ly/3qUymuF or dial (631) 992-3221, Access Code: 160-249-796 to join the meeting. A brief presentation followed by questions and comments will be held from 5:00 p.m. to 5:30 p.m., and again from 5:30 p.m. to 6:00 p.m. Please note questions and comments may be submitted via the online chat for the project team to address directly.
· The In-Person Construction Open House will be held from 6:00 p.m. to 7:00 p.m. at the Old Fort Pierce City Hall, Second Floor, located at 315 Avenue A, Fort Pierce, FL 34950. This meeting will have an informal open house format, with project representatives available to answer questions and address comments at any time during the meeting. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

INDIAN RIVER COUNTY

(City of Vero Beach, Vero Beach, Indian River Shores, Sebastian, Wabasso, Wabasso Beach, City of Fellsmere)

17. State Road A1A and SR 5/US 1 Roadway Improvements Project
Description: This roadway improvements project began August 26, 2022.The SR A1A from south of Jasmine Lane to north of SR 60/Beachland Boulevard project improvements consist of repaving and restriping the existing asphalt pavement; widening the roadway to accommodate a 7-foot buffered bicycle lane; constructing a 6-foot sidewalk on the east side (northbound direction); upgrading drainage, signage and pavement markings; upgrading existing curb ramps to meet Americans with Disabilities Act (ADA) standards; adding two signalized pedestrian mid-block crossings at Iris Lane and Dahlia Lane; and, upgrading pedestrian signal and lighting at the intersection of SR A1A and SR 60/Beachland Boulevard. SR A1A and SR 5/US 1 turn lanes project improvements consist of constructing a southbound right turn lane at the intersection of SR 5/US 1 and 8th Street; extending the southbound right turn lane at the intersections of SR A1A and the 17th Street Causeway and SR A1A and SR 60/Beachland Boulevard; and upgrading existing drainage.
Cost/Completion: $5.6 million. Completion is anticipated early 2024.
Traffic Impact:

  • The northbound shoulder of SR A1A between Jasmine Lane and Banyan Road will be closed from 9 a.m. to 3:30 p.m., through November 2023, for sod installation. Only one direction will be closed at a time.
  • The northbound lane of SR A1A between Jasmine Lane and Banyan Road will be closed 9 a.m. to 3:30 p.m., Monday through Friday, through November 2023, for deliveries. Flagging operations will be in place to direct motorists. Only one direction will be closed at a time. 
  • The southbound lane of SR A1A between Jasmine Lane and Banyan Road will be intermittently closed from 9 a.m. to 3:30 p.m., Monday through Friday, through November 2023, for deliveries. Flagging operations will be in place to direct motorists. Only one direction will be closed at a time.
  • The outside southbound lane of SR 5/US 1 from 12th Street to 8th Street and the SR 5/US 1 access onto westbound 8th Street will be closed around-the-clock through November 2023 for drainage work and construction of a dedicated right-turn lane at the intersection of SR 5/US 1 and 8th Street. Motorists on SR 5/US 1 can make a right turn onto westbound 8th Street at the traffic signal. One southbound SR 5/US 1 through lane will remain open to traffic at all times. Access to properties will be maintained.
  • The southbound lane on SR A1A between Jasmine Lane and Banyan Road will be closed beginning Tuesday Nov. 6 through Tuesday Nov. 21, from 9 a.m. to 3:30 p.m., for roadway widening and deliveries. A flagging operation will be in place to assist motorists. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

18. State Road 510/Wabasso Beach Road Bridge Railing Safety Improvements Project
Description: This bridge railing safety improvements project began March 31, 2023. The project improvements consist of installing pedestrian/bicycle railing on the north and south sides of the existing SR 510/Wabasso Beach Road bridge.
Cost/Completion: $1.4 million. Final accepted on October 25, 2023.
Traffic Impact:

· No lane closures. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

19. State Road 656/17th Street East End of Bridge Rehabilitation and Improvements Project
Description: Construction is anticipated to begin August 28, 2023. The project improvements consist of replacement of the eastern 400 feet of the existing bridge; sealing the full length of the existing bridge deck surface; and upgrading signing and pavement markings.
Cost/Completion: $22.3 million. Completion anticipated summer 2028.
Traffic Impacts:

  • One eastbound and westbound lane of SR 656/17th Street from Indian River Boulevard to Indian Bay Drive will be closed from 9 p.m., to 7 a.m., Monday, Oct. 2 through Sunday, Nov. 5 for lane separator repair. Flaggers will be utilized to maintain traffic going eastbound and westbound.
  • One eastbound lane of SR 656/17th Street between 4th Avenue and Indian River Boulevard will be closed around-the-clock beginning at 9 p.m., Monday, Aug. 28 through 12 a.m., Monday, April 14, 2025, for bridge construction activities.
  • One westbound lane of SR 656/17th Street between E Camino Del Rio and Indian Bay Drive will be closed around-the-clock beginning at 9 p.m., Monday, Aug. 28 through 12 a.m., Monday, April 14, 2025, for roadway work.
  • One southbound outside turn lane on Indian River Boulevard to eastbound SR 656/17th Street may be closed around-the-clock beginning at 9 p.m., Monday, Aug. 28 through 12 a.m. Monday, April 28, 2025, for bridge construction activities.
  • One eastbound and westbound lane will be open in each direction on the south side of the bridge. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479. 

20. CR 612/8th Street over Lateral Canal C (Bridge No. 884024) Bridge Replacement Project
Description: Construction began June 5, 2023. Project improvements consist of replacing the existing two-lane bridge (No. 884024) over Lateral Canal C, dredging Lateral Canal C to accommodate new bridge construction, installing guardrail to shield the canal hazards, and upgrading signing and pavement markings.
Cost/Completion: $6.9 million. Anticipated completion spring 2024.
Traffic Impacts:

· Eastbound and westbound CR 612/8th Street over Lateral Canal C Bridge No. 884024 from west of 74th Avenue to east of Lateral Canal C is closed around-the-clock through spring 2024, for bridge replacement work.

Detour Information:

    • Eastbound CR 612/8th Street motorists will be detoured via 82nd Avenue, 16th Street and 66th Avenue to CR 612/8th Street.
    • Westbound CR 612/8th Street motorists will be detoured via 66th Avenue, 16th Street and 82nd Avenue to CR 612/8th Street.
    • Northbound 74th Avenue motorists will be detoured via 4th Street, 66th Avenue and 16th Street to 74th Avenue.
    • Southbound 74th Avenue motorists will be detoured via 16th Street, 66th Avenue and 4th Street to 74th Avenue. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

21. State Road (SR) 9/I-95 at County Road (CR) 606/Oslo Road New Interchange and CR 606/Oslo Road Widening Project
Description: The project is anticipated to begin August 14, 2023. In partnership with Indian River County, FDOT is pleased to announce the construction of the new interchange at SR 9/I-95 and CR 606/Oslo Road and CR 606/Oslo Road improvements. Additionally, CR 606/Oslo Road will have capacity improvements to four lanes from west of SR 9/I-95 to 58th Avenue per Indian River County Resolution Nos. 2017-022 and 2017-023. Project improvements consist of constructing a new interchange with partial cloverleaf ramps at SR 9/I-95 and CR 606/Oslo Road, widening CR 606/Oslo Road from two-lane to a four-lane divided roadway from west of SR 9/I-95 to SW 58th Avenue, installing interchange ramp lighting, replacing the existing CR 606/Oslo Road bridge over SR 9/I-95, installing a new signalized intersection at CR 606/Oslo Road and 66th Avenue SW, installing intersection lighting at 74th Avenue, 66th Avenue and 58th Avenue, realigning 82nd Avenue at CR 606/Oslo Road, eliminating the 86th Avenue connection to CR 606/Oslo Road, constructing 13th Street SW to connect 86th Avenue SW and 90th Avenue, extending the south limit the existing noise wall on SR 9/I-95, replacing Indian River County sanitary, water and raw water mains, upgrading signing, signalization, intersection lighting, bicycle lanes, and sidewalks, installing a closed drainage system and constructing three drainage ponds.
Cost/Completion: $95.78 million. Anticipated completion in summer 2027.
Traffic Impacts:

  • No lane closures. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

 22. SR 5/US 1 Resurfacing Project, from North of 6th Avenue to 12th Street
Description: This 0.721-Mile project is anticipated to begin August 17, 2023. The project improvements consist of milling and resurfacing the existing roadway, installing new sidewalks in areas where they are currently missing, installing bike lanes throughout the project limits, upgrading pedestrian curb ramps to meet Americans with Disabilities Act (ADA) standards, upgrading lighting at the intersections of 8th Street and 12th Street to improve pedestrian lighting at the crosswalks, upgrading pedestrian signalization at the intersections of 8th Street and 12th Street, and upgrading signage and pavement markings.
Cost/Completion: $2.84 million. Anticipated completion in spring 2024.
Traffic Impacts:

  • One southbound lane on SR 5/ US 1 between 6th Street and 12th Street will be closed from 9 a.m. to 4 p.m., beginning Monday, Nov. 6 through Thursday, Nov. 9, for utility work. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

23. SR 5/US 1 Resurfacing Project, from Harrison Street to South of Davis Street
Description: This 1.472-mile project is anticipated to begin August 17, 2023. The project improvements consist of milling and resurfacing the existing roadway, replacing sidewalk and providing sidewalk connectivity and continuity, removing abandoned driveways, upgrading pedestrian curb ramps to meet Americans with Disabilities Act (ADA) standards, upgrading pedestrian signalization and lighting at signalized intersections, and upgrading drainage, signage and pavement markings.
Cost/Completion: $3.9 million. Anticipated completion in Spring 2024.
Traffic Impacts:

  • One northbound lane on SR 5/US 1 between Harrison Street and Davis Street may be closed nightly from 8 p.m. to 6 a.m., Monday through Friday, through November 2023 for roadway work.
  • One northbound lane of SR 5/US 1 between Harrison Street and Davis Street may be intermittently closed from 4 a.m. to 11 a.m. and 2 p.m. to 4:30 p.m., Monday, Nov. 6 through Thursday, Nov. 9, to remove the sidewalk and curb removal and installation, and grading for sod. For more information, please contact Community Outreach Specialist Samantha Kayser at 772-579-5479.

MAINTENANCE, UTILITY, PERMIT & ADDITIONAL AGENCY PROJECTS 

MARTIN COUNTY

(Hobe Sound, Palm City, City of Stuart, Stuart, Jensen Beach, Jupiter Island, Port Salerno, Port Mayaca, Rio, Indiantown, Tequesta, Town of Sewall’s Point)    

INDIANTOWN:
Eastbound and Westbound SW Kanner Highway between Port Mayaca Cemetery and King Ranch, in Indiantown, 9 a.m. to 4 p.m., Monday, Oct. 23 through Friday, Dec. 22, 1 lane will be closed either direction, from for FPL Fiber Development. For more information, please contact Rafael Ureña at 772-882-5084. 

PALM CITY:
Westbound Southeast Ocean Boulevard at intersection of North River Road, in Palm City, 9 a.m. to 4 p.m., Monday through Friday, Monday, Oct. 30 through Friday, Dec. 22, 1 of 2 lanes closed, for utility pole, directional boring, equipment cabinet installation. For more information, please contact Mark Meyers at 954-560-0450.

SEWALL'S POINT:
Eastbound and westbound SE Ocean Boulevard over the Evans Crary Bridge, in Sewall’s Point, 9 a.m. to 4 p.m., Wednesday, Nov. 15 through Friday, Nov. 17, 1 of 2 lanes closed, for routine maintenance. For more information, please contact Guillermo Canedo, Communications Manager, FDOT District Four at 954-777-4302.

STUART:
Northbound Kanner Highway between SE Bloxham Way and SW Pomeroy Street, in Stuart, 9 a.m. to 4 p.m., Wednesday, Oct. 18 through Thursday, Nov. 9, 1 of 3 lanes will be closed for utility Work. For more information, please contact Steve Summas at 305-345-7073.

Northbound Kanner Highway between Crestwood Circle and Salerno Road, in Stuart, 9 a.m. to 4 p.m., Wednesday, Nov. 1 through Sunday, Dec. 31, 1 of 3 lanes closed, for utility work. For more information, please contact Brittany Kiernan at 772-286-7385.

Eastbound SR 714 between SE Rays Way and US 1, in Stuart, 9 a.m. to 4 p.m., Monday, Nov. 13 through Friday, Nov. 17, 1 of 2 lanes closed, for directional boring work. For more information, please contact Michael Lewkutz at 561-248-4374.    

ST. LUCIE COUNTY

(City of Port St. Lucie, Port St. Lucie, White City, City of Fort Pierce, Fort Pierce, Okeechobee, St. Lucie West, Tradition)

FORT PIERCE:

Eastbound and westbound Seaway Drive over the South Bridge Causeway, in Fort Pierce, 9 a.m. to 4 p.m., Tuesday, Nov. 7 through Thursday, Nov. 9, 1 of 2 lanes closed, for routine maintenance. For more information, please contact Guillermo Canedo, Communications Manager, FDOT District Four at 954-777-4302.

Northbound and southbound US 1 between Juanita Avenue and Old US 1 highway, in Fort Pierce, 9 a.m. to 4 p.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts, for Caliber Car Wash Construction. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound and southbound Turnpike Feeder Road between Indrio Road and US 1, in Fort Pierce 9 a.m. to 4 p.m., Monday, Oct. 30, through Friday, Dec. 22, 1 lane will be closed either direction closed with possible lane shifts or flagging operation at times, for FP&L utility installation and wiring operations. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound US 1 between Harbor Branch Way and SE 21st Street in Fort Pierce, 9 a.m. to 4 p.m., Monday, Oct. 30, through Friday, Dec. 22, 1 of 2 lanes may be closed with possible lane shifts at times, for FP&L utility installation and wiring operations. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound and southbound SR A1A access to Porpoise Avenue, in Fort Pierce, around-the-clock beginning at 8 a.m. to 4 p.m., Thursday, Nov. 2 through Thursday Nov. 9, all lanes closed, for utility work. Northbound SR A1A traffic will be detoured to Francis Avenue, Hernando Street, and Porpoise Avenue. Southbound traffic will be detoured to Avalon Avenue, Hernando Street, and Porpoise Avenue. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound US Highway 1 between Tumblin Kling Road and Pleasure Avenue, in Fort Pierce, 9 a.m. until 4 p.m., Monday through Friday, Monday, Oct. 23 through Wednesday, Nov. 22, 1 of 2 lanes closed, for directional boring, handhole and conduit installation. For more information, please contact Israel Lopez at 786-380-2377.

Southbound US Highway 1 between South Market Avenue and West White City Road, in Fort Pierce, 9 a.m. until 3 p.m., Monday through Friday, Monday, Oct. 23 through Wednesday, Nov. 22, 1 of 2 lanes closed, for directional boring, handhole and conduit installation. For more information, please contact Israel Lopez at 786-380-2377.

Northbound and southbound US 1 Highway 1 between Midway Road and Sunshine Boulevard, in Fort Pierce, 9 a.m. to 4 p.m., Monday, Nov. 6 through Thursday, Nov. 9, 1 of 7 lanes closed, for utility work. For more information, please contact Chris Rollins at 561-891-5727.

PORT ST. LUCIE:
Southbound northwest Federal Highway between Lenard Road and 10855 South US Highway 1, in Port St. Lucie, 9 a.m. until 3:30 p.m., Monday, Nov. 6 through Wednesday, Nov. 8, 1 of 2 lanes closed, for directional boring installation. For more information, please contact Latess Hill 561-631-0663. 

Northbound Dixie Highway between Savanna Club Boulevard and Spanish Lakes Road, in Port St Lucie, 9 a.m. until 4 p.m., Monday through Friday, Monday, Oct. 30 through Friday, Nov. 17, 1 of 3 lane closed, for watermain relocation. For more information, please contact Jordan Bails 954-829-4443.

Northbound and Southbound US 1 between Savanna Club Boulevard and Westmoreland Boulevard, in Port St. Lucie, 9 a.m. to 4 p.m., Monday, Nov. 6 through Thursday, Nov. 9, 2 of 6 lanes closed, for median excavation and irrigation installation for landscaping work. For more information, please contact Lisandro Iglesias at 786-519-5807.

Northbound US 1 between Walton Road and SE Huffman Road, in Port St. Lucie, 9 a.m. to 4 p.m., Monday, Nov. 6 through Friday, Nov. 22, 1 of 3 lanes may be intermittently closed with possible lane shifts, for FP&L utility installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

Eastbound Crosstown Parkway at US 1, in Port Saint Lucie, 9 a.m. to 4 p.m., Monday Nov. 6 through Friday Nov. 22, 1 of 3 lanes may be intermittently closed, for FP&L utility installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

TRADITION:
Eastbound and westbound Gatlin Boulevard between Village Parkway and Savona Boulevard and northbound and southbound at the intersections of Village Parkway, Brescia Street, Savage Boulevard, Import Drive, Rosser Boulevard and Savona Boulevard, in Tradition, 9 a.m. to 3:30 p.m., Monday, Nov. 6 through Thursday, Nov. 9, 2 of 6 lanes closed, for intersection work. For more information, please contact Jerry Stine at 772-577-9765.

INDIAN RIVER COUNTY

(City of Vero Beach, Vero Beach, Indian River Shores, City of Sebastian, Sebastian, Wabasso, Wabasso Beach, Orchid Island, City of Fellsmere)

INDIAN RIVER SHORES:  
Northbound and southbound SR A1A between Turtle Beach Road and Palm Island Lane, in Indian River Shores, 9 a.m. to 4 p.m., Monday, Nov. 6 through Thursday, Nov. 9, 1 of 2 lanes may be closed with possible lane shifts or flagging operation at times, for FP&L utility pole installation and wiring operations. For more information, please contact Rafael Ureña at 772-882-5084.  

Northbound and southbound SR A1A between Turtle Beach Road and Palm Island Lane, in Indian River Shores, 9 p.m. to 6 a.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be closed with possible lane shifts or flagging operation at times, for FP&L utility pole installation and wiring operations. For more information, please contact Rafael Ureña at 772-882-5084.  

Northbound and southbound SR A1A between Old Winter Beach Road and Turtle Beach Road, in Indian River Shores, 9 p.m. to 6 a.m., Monday, Nov. 6 through Thursday, Nov. 9, 1 of 2 lanes may be closed with possible lane shifts or flagging operation at times, for FP&L utility pole installation and wiring operations. For more information, please contact Rafael Ureña at 772-882-5084.  

Northbound and southbound SR A1A between Old Winter Beach Road and Turtle Beach Road, in Indian River Shores, 9 a.m. to 4 p.m., Monday, Nov. 6 through Thursday, Nov. 9, 1 of 2 lanes may be closed with possible lane shifts or flagging operation at times, for FP&L utility pole installation and wiring operations. For more information, please contact Rafael Ureña at 772-882-5084. 

VERO BEACH:
Northbound and southbound SR A1A between Beachcomber Lane and Bahia Mar Road, in Vero Beach, 9 a.m. to 4 p.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts and or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084. 

Eastbound and westbound E Causeway Boulevard between Indian Bay Drive and Club Drive, in Vero Beach, 9 a.m. to 4 p.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts and/or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084. 

Eastbound and westbound E Causeway Boulevard between Indian Bay Drive and Club Drive, in Vero Beach, 9 p.m. to 6 a.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts and/or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound and southbound SR A1A between Lake Drive and Sandpiper Lane, in Vero Beach, 9 a.m. to 4 p.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts and/or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound and southbound SR A1A between Lake Drive and Sandpiper Lane, in Vero Beach, 9 p.m. to 6 a.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts and/or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound and southbound SR A1A between Beachcomber Lane and Bahia Mar Road, in Vero Beach, 9 p.m. to 6 a.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts and/or flagging operations, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

Eastbound and westbound SR 60 between 32nd Avenue and 22nd Avenue, in Vero Beach, 9 a.m. to 4 p.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 3 lanes closed, for installation and/or replacement of FPL poles. For more information, please contact Rafael Ureña at 772-882-5084.

Eastbound and westbound SR 60 between 32nd Avenue and 22nd Avenue, in Vero Beach, 9 p.m. to 5 a.m., Monday, Nov. 6, through Thursday, Nov. 9, 2 of 3 lanes closed, for installation and/or replacement of FPL poles. Officers will be present to assist with the safe transition into 1 lane. For more information, please contact Rafael Ureña at 772-882-5084.

Eastbound and westbound Beachland Boulevard between Flamingo Drive and Indian River Drive E, in Vero Beach, 9 a.m. to 4 p.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 3 lanes closed, for installation and/or replacement of FPL poles. For more information, please contact Rafael Ureña at 772-882-5084.

Westbound 17th Street between 6th Avenue and 10th Avenue, in Vero Beach, 9 a.m. to 4 p.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

Westbound 17th Street between 6th Avenue and 10th Avenue, in Vero Beach, 9 p.m. to 6 a.m., Monday, Nov. 6, through Thursday, Nov. 9, 2 of 3 lanes may be intermittently closed with possible lane shifts, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound US 1 between 16th Place and 18th Street in Vero Beach, 9 p.m. to 6 a.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

Northbound US 1 between 16th Place and 18th Street, in Vero Beach, 9 a.m. to 4 p.m., Monday, Nov. 6, through Thursday, Nov. 9, 1 of 2 lanes may be intermittently closed with possible lane shifts, for FP&L pole installation operations. For more information, please contact Rafael Ureña at 772-882-5084.

For around-the-clock, real-time, I-95 traffic information, visit: www.fl511.com.

For updated lane closure information, please refer to: www.d4fdot.com.

Learn more about the Florida Department of Transportation at: www.fdot.gov.