Florida - Monday January 30, 2023: Here is the latest update from Brightline about bridge work, lane and railroad crossing closures, during the ongoing construction and testing of the companies high speed rail service which they hope to extend all the way to Orlando, from Miami, this year.
Motorists and watercraft should proceed with extra caution through work zones and adhere to posted detour signs, speed limits and other signage.
ORLANDO EXTENSION (ORLANDO to WEST PALM BEACH)
Orange County
Beachline Expressway/SR 528
Eastbound Beachline Expressway/SR 528 between Narcoossee Rd. and SR 417 (milepost 13-15)
Continuous daytime shoulder closure, 6:30 a.m. to 5 p.m.
Eastbound Beachline Expressway/SR 528 between SR 417 and Innovation Way (milepost 16-18)
Continuous daytime shoulder closure, 6:30 a.m. to 5 p.m.
Eastbound Beachline Expressway/SR 528 between Dallas Blvd. and SR 520 (milepost 27-28)
Continuous daytime shoulder closure, 7 a.m. to 7 p.m.
Westbound Beachline Expressway/SR 528 between SR 520 and Dallas Blvd. (milepost 28-27)
Continuous daytime shoulder closure, 7 a.m. to 7 p.m.
Beachline Expressway/SR 528, Goldenrod Rd. and Narcoossee Rd.
Eastbound Beachline Expressway/SR 528 between Goldenrod Rd. and SR 417 (milepost 12-15)
Continuous daytime shoulder closure, 7 a.m. to 7 p.m.
Eastbound Beachline Expressway/SR 528 exit ramp to Narcoossee Rd. (Exit 13)
Continuous daytime shoulder closure, 7 a.m. to 7 p.m.
Narcoossee Rd. entrance ramp to Eastbound Beachline Expressway/SR 528
Continuous daytime shoulder closure, 7 a.m. to 7 p.m.
Beachline Expressway/SR 528 and SR 417
Northbound SR 417 exit ramp to Eastbound/Westbound Beachline Expressway/SR 528 (Exit 26)
Continuous daytime shoulder closure, 7 a.m. to 7 p.m.
Brevard County
Beachline Expressway/SR 528
Eastbound Beachline Expressway/SR 528 (milepost 40-42)
Single lane closures:
• Weekdays: 9 a.m. to 5 p.m., through Friday, February 27.
Nighttime, single lane closure:
• Weekdays: 10 p.m. to 5 a.m., through Friday, February 27.
Westbound Beachline Expressway/SR 528 (milepost 40 – 42 & milepost 45 – 46)
Daytime, single lane closure:
• Weekdays: 7 a.m. to 4 p.m., through Friday, February 27.
Night-time, single lane closure:
• Weekdays: 10 p.m. to 5 a.m., through Friday, February 27.
Westbound Beachline Expressway/SR 528 entrance ramp to northbound I-95
Night-time closure to pave mainline Beachline Expressway/SR 528.
• 10 p.m., to 5 a.m., Thursday, February 2 to Friday, February 3
Detour information:
• Westbound Beachline Expressway/SR-528 traffic wishing to access northbound I-95 will be directed to utilize westbound SR-528 exit 42A towards southbound I-95, access eastbound Beachline Expressway/SR-528 via exit 205A and travel eastbound on Beachline Expressway/SR 528 to exit 42B to access northbound I-95.
Industry Rd. entrance ramp to westbound Beachline Expressway/SR 528
Night-time ramp closure to pave mainline Beachline Expressway/SR 528.
• 10 p.m., to 5 a.m., Monday, January 30 to Tuesday, January 31,
• 10 p.m., to 5 a.m., Tuesday, January 31 to Wednesday, February 1 and
• 10 p.m., to 5 a.m., Wednesday, February 2 to Thursday, February 3.
Detour information:
• Industry Rd. traffic wishing to access westbound Beachline Expressway/SR 528 will be directed to travel north on Industry Rd. to Cidco Rd., travel east on Cidco Rd. to US-1 and travel south on US-1 to access westbound Beachline Expressway/SR 528.
Crossings / Road Closures
Melbourne - Railroad Crossing at Lake Washington Rd.
Full road closure until 7 p.m., Friday, February 10.
Detour Information:
• Eastbound Lake Washington Rd. traffic will be directed to travel north on Stewart Rd. to Parkway Dr., travel east on Parkway Dr. to US-1 and travel south on US-1 to access Lake Washington Rd.
• Westbound Lake Washington Rd. traffic will be directed to travel north on US-1 to Parkway Dr. travel west on Parkway Dr. to Stewart Rd. and travel south on Stewart Rd. to Lake Washington Rd.
Melbourne - Railroad Crossing at Eau Gallie Blvd.
Full road closure 7 a.m., Friday, February 17 to 7 p.m., Monday, February 27.
Detour Information:
• Eastbound Eau Gallie Blvd. traffic will be directed to travel south on Apollo Blvd. to Sarno Rd., travel east on Sarno Rd. to US-1 and travel north on US-1 to Eau Gallie Blvd.
• Westbound Eau Gallie Blvd. traffic will be directed to travel south on US-1 to Sarno Rd., travel west on Sarno Rd to Apollo Blvd. and travel north on Apollo Blvd to Eau Gallie Blvd.
Melbourne - Railroad Crossing at Prospect Ave. (LONGTERM CLOSURE)
Full road closure through February 2023 for bridge work at Crane Creek. Crossing will be fully closed until completion of work.
Detour Information:
• Eastbound Prospect Ave. traffic will be directed to Stone St., travel south on Stone St. to WH Jackson St., travel east on WH Jackson St. to US-1 and travel north on US-1 to access Prospect Ave.
• Westbound Prospect Ave. traffic will be directed to US-1, travel south on US-1 to WH Jackson St., travel west on WH Jackson St. to Stone St. and travel north on Stone St. to access Prospect Ave.
Bridges
Melbourne - Eau Gallie River
Daytime bridge work operations, including pile driving, Monday through Sunday, 7 a.m. to 7 p.m., continuing through Q1 2023 to construct a railroad bridge on the east side of the new active railroad bridge.
Melbourne - Crane Creek
Daytime bridge work operations, including pile driving, Monday through Sunday, 7 a.m. to 7 p.m., continuing through Q1 2023 to construct a railroad bridge on the west side of the new active railroad bridge (southwest bank).
Palm Bay - Turkey Creek
Daytime bridge work operations, including pile driving, Monday through Sunday, 7 a.m. to 7 p.m., continuing through Q1 2023 to construct a railroad bridge on the east side of the new active railroad bridge.
Brevard and Indian River Counties
Bridges
Sebastian - Sebastian River
Daytime bridge work operations, including pile driving and demolition work, Monday through Sunday, 7 a.m. to 7 p.m., continuing through Q1 2023 to construct a railroad bridge on the east side of the new active railroad bridge.
Indian River County
Railroad Crossings
Vero Beach - Railroad Crossing at Aviation Blvd. (32nd St.)
Full road closure through 7 p.m., Friday, February 17.
Detour Information
• Eastbound Aviation Blvd. (32nd St.) traffic will be directed to travel south on 43rd Ave. to 20th St., travel east on 20th St. to 11th Ave., travel north on 11th Ave. to 21st St., travel west on 21st St. to US-1 and travel north on US-1 to Aviation Blvd. (32nd St.).
• Westbound Aviation Blvd. (32nd St.) traffic will be directed to travel south on US-1 to 20th St., travel west on 20th St. to 43rd Ave. and travel north on 43rd Ave. to Aviation Blvd. (32nd St.).
St. Lucie County
Railroad Crossings
Port St. Lucie - SE Walton Rd.
Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit SE Walton Rd.
St. Lucie and Martin Counties
High Speed Testing up to speeds of 110 mph
Daytime testing, 7 a.m. to 7 p.m., through Wednesday, February 8. Flaggers will be present at the following railroad crossings where trains will operate at high speeds.
St. Lucie County
• Walton Rd.
• Riverview Dr.
Martin County
• County Line Rd.
• Skyline Dr. (CR 722)
• Pitchford Landing
Martin County
Railroad Crossings / Lane Closures
Jensen Beach – Riverview Dr.
Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit Riverview Dr.
Jensen Beach -County Line Rd.
Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit County Line Rd.
Jensen Beach - Skyline Dr.
Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit County Line Rd.
Jensen Beach - NE Jensen Beach Blvd.
Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit NE Jensen Beach Blvd.
Jensen Beach - NE Dixie Hwy.
Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit NE Dixie Hwy.
Stuart - Alice St.
Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit NW Alice St.
Stuart - NW Fern St.
Daytime flagging operations, 7 a.m. to 5 p.m. for rail work. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit NW Fern St.
Stuart - Railroad Crossing at Decker Ave.
Full road closure, 7 a.m., Friday, February 17 to 7 p.m., Monday, February 27.
Detour Information
• Southbound Decker Ave. traffic will be directed to travel west on Florida St. to Johnson Ave., travel south on Johnson Ave. to US-1, and travel south on US-1 to Decker Ave.
• Northbound Decker Ave. traffic will be directed to travel north on US-1 to SR5a, travel east on SR5a to Dixie Hwy./A1A and travel south on Dixie Hwy./A1A to Decker Ave.
Stuart -West of SE Dixie Hwy./A1A between SE Decker Ave. and SE Monterey Rd.
Daytime southbound shoulder closures for concrete pouring, Monday to Friday, 7 a.m. to 3 p.m.
Stuart - Southbound A1A from south of SE Cove Rd. to south of SE Alicia St.
Continuous shoulder closure through Q1 2023.
Palm Beach County
High Speed Testing up to speeds of 110 mph
Daytime testing, 7 a.m. to 7 p.m., beginning Saturday, February 11 and continuing through March. Flaggers will be present at the following railroad crossings where trains will operate at high speeds.
Palm Beach County
● Center St. (SR A1A)
● Indiantown Rd. (SR 706)
● Toney Penna Dr.
● Frederick Small Rd.
● Donald Ross Rd.
● Hood Rd.
● Kyoto Gardens Dr.
● RCA Blvd.
● Burns Rd.
● Lighthouse Dr.
● Richard Rd.
● North Lake Blvd. (SR 809)
● Park Ave.
● Silver Beach Rd.
● Blue Heron Blvd. (SR 708)
● Flagler St. (West 13th St.)
● Inlet Blvd./MLK Jr. Blvd. (SR 710)
● 49th St.
● 45th St. (CR 702)
● 36th St.
● 30th St.
● 25th St.
● 23rd St.
● 15th St.
Railroad Crossings / Lane Closures
Jupiter- Riverside Dr. and Alternate A1A
Daytime flagging operations, 7 a.m. to 5 p.m. to move materials for bridge construction, continuing through Q1 2023. Crossings may be closed briefly (1-2 minutes) as trucks enter and exit the right of way.
Bridges
Jupiter - Loxahatchee River
Daytime bridge work operations, 7 a.m. to 7 p.m., Monday through Sunday, continuing through Q1 2023 for bridge construction.
Railroad construction information can also be found online at: https://www.gobrightline.com/railroad-construction.